Canillo presents the refurbishment of Soldeu village centre, with works planned from April 2027 to November 2028
On 24 November the Comú de Canillo presented to Soldeu residents a plan to refurbish the village centre along 415 metres of the CG-2 main road. The official note was issued that day at 17:55 (Europe/Andorra). Pavement area is to rise from 1,943 m² to 3,150 m², a 62% increase, and the asphalt surface is to be cut by 20% (1,227 m² less). Bus stops will move from the centre to the entrance and exit of the village, with more capacity, to improve traffic flow and the link with the ski slopes at Grandvalira, the club's sponsor. Cònsol major Jordi Alcobé also set out a new layout for parking and the renewal of underground utilities. The tender is planned for January–February 2027; works are due to start on 1 April 2027 and to finish, as a guide date, on 30 November 2028.